A Part 135 air carrier certificate can be created from scratch. The labor-intensive tasks are:
Define the proposed operation.
Prepare comprehensive operations, maintenance, and training manuals.
Show compliance with FAA regulations and guidance requirements.
Hire, train, and qualify flight crew and maintenance personnel.
Complete FAA approval tasks.
|
| Phase | FAA Phase | Applicant / FAA Activity | Gate |
|---|---|---|---|
| 1 | Pre-application | Define the proposed operation, begin the application, and meet with the FAA certification team. | Gate 1 |
| 2 | Formal Application | Submit the application package, manuals, training curricula, compliance statement, management qualifications, proposed OpSpecs, and applicable ED DCTs. | Gate 2 |
| 3 | Design Assessment | FAA evaluates the manuals, programs, procedures, and supporting compliance evidence. | |
| 4 | Performance Assessment | Demonstrate that the aircraft, personnel, training, procedures, and operating systems work as designed. | Gate 3 |
| 5 | Administrative Functions | FAA completes the certification record and issues the certificate and Operations Specifications. | Certificate |
| Start From Scratch | Acquire an Existing Part 135 Charter Company |
|---|---|
Meet operator requirements.
Create manuals and programs.
Complete DCTs and compliance work.
Establish FAA-approved operating systems.
|
Meet operator requirements.
Onboard qualified airmen.
Add the buyer's aircraft.
Modify the existing operation as needed.
|
| Manuals and Training | Design Compliance / DCTs |
|---|---|
General Operations Manual
General Maintenance Manual
Company Training Manual
Aircraft-Specific Training Manual
Minimum Equipment List
International Flight Operations Manual
Flight Attendant Manual, if applicable
|
Review each applicable FAA question.
Identify the regulation and guidance.
Locate the exact manual section.
Enter the manual reference.
Add the supporting manual text.
Explain why a question is not applicable.
Correct any item that cannot be answered Yes.
|
A Data Collection Tool (DCT) is a group of related FAA compliance questions. The applicable DCTs depend on the proposed operation.
| Organizational Management |
Flight Operations |
Operations Management |
Technical Operations |
Onboard Operations |
Ground Operations |
|---|---|---|---|---|---|
Safety Program
Required Personnel
Manual Management
Electronic Records
Safety Policy
Safety Risk Management
Safety Assurance
Safety Promotion
|
Flightcrew Training
Check Pilots/Instructors
Simulators
Outsource Training
Airmen Qualifications
Flight/Duty/Rest
Flight Deck Procedures
Recent Experience
|
Aircraft Performance
Areas/Routes/Airports
Special Navigation
Operational Control
Weight & Balance
MEL/CDL/NEF
Flight Planning
Extended Operations
|
Maintenance Personnel
Maintenance Training
Inspection Requirements
Inspection Schedule
AD Management
Recordkeeping
Airworthiness Release
Repairs/Alterations
|
Flight Attendant Training
Duty/Rest
Cabin Procedures
Carry-on Baggage
Exit Seating
Passenger Handling
|
Station Training
Hazmat Training
Fueling
Line Stations
Cargo Handling
Hazardous Materials
Ground Icing |
76 DCTs |
1,324 Compliance Questions |
| The scope may vary. | |
| DCT Example | Questions | Relative Size |
|---|---|---|
| Recent Experience | 9 | ███ |
| Manual Management | 16 | ██████ |
| Training of Flight Crewmembers | 35 | █████████████ |
| Airman Duties / Flight Deck Procedures | 69 | ██████████████████████████ |
| Answer | Yes or Not Applicable. A No answer identifies an item that must be corrected. |
| Manual Reference | Identify the manual and exact location so the FAA inspector can find the supporting procedure. |
| Supporting Comment | Include the supporting manual text when practical so the inspector does not need to search for it. |
| Not Applicable | Explain why the question does not apply to the proposed operation. |
Creating a certificate from scratch is a tradeoff between time, cost, and reliability.
The major work products are FAA approved.
Flight crew and maintenance personnel must be trained and qualified.
Aircraft compliance must be demonstrated.
The buyer's team is supported by experienced USAC specialists.
|
In a well-prepared acquisition, the goal is to have the buyer operating in approximately 3 to 6 months, subject to FAA availability, aircraft readiness, and completion of required transition work.
Part 135 Air Carrier and Operator Certification
Part 135 Certification Process