Air Carrier Certification |
Proving and validation demonstrate that the operator can use its aircraft, people, manuals, training, and operating systems safely and in compliance with Part 135.
| Test | When It Applies | Purpose |
|---|---|---|
| Proving Tests | Generally required when the certificate holder has not previously proved a turbojet airplane, or another aircraft for which two pilots are required for VFR operations, under Part 135. | Full-scale simulation of the proposed revenue operation. |
| Validation Tests | Required for specified new aircraft and authorizations, including certain international operations, Class II navigation, and special performance or operational authorizations. | Demonstrate that the operator can safely conduct the specific operation or authorization. |
When required by 14 CFR 135.145, proving tests include at least 25 hours acceptable to the FAA.
Five hours of night operations if night operations will be authorized.
Five instrument approaches under simulated or actual conditions if IFR operations will be authorized.
Operations into a representative number of en route airports determined by the FAA.
Passengers are not carried except persons needed for the test or FAA-designated observers.
| Area | Demonstration |
|---|---|
| Operational Control | Dispatch/release decisions, flight following, weather, maintenance status, crew qualification, and management oversight. |
| Flightcrew | Use of company procedures, checklists, MEL, abnormal procedures, CRM, and aircraft-specific training. |
| Maintenance | Aircraft status, maintenance control, discrepancies, return-to-service procedures, and required records. |
| Manuals and Software | The procedures and operating tools work in actual operations as described in the approved manuals. |
| Airports / Areas | The operator can safely conduct the routes, airports, navigation, and special operations requested. |
The FAA may use an acceptable demonstration method other than an actual flight when the operator can demonstrate competence and compliance without flying. Proving and validation tests may also be conducted at the same time when appropriate.
Aircraft conformity complete and discrepancies corrected.
Manuals and applicable programs approved or accepted.
Flightcrew and required personnel trained, checked, and current.
MEL, maintenance control, dispatch, flight-following, and record systems operational.
Required airports, routes, scenarios, and special authorizations included in the demonstration plan.
Schedule of Events coordinated with the FAA certification team.
| Question | Why It Matters |
|---|---|
| Is proving required? | A new turbojet operation can require at least 25 hours of proving before revenue operation. |
| What must be validated? | Aircraft, international areas, Class II navigation, or special authorizations may trigger validation work. |
| Is the operation ready before the test? | Proving runs are intended to demonstrate an operating system, not finish building one. |
| Can demonstrations be combined? | The FAA may permit proving and validation to be accomplished together when appropriate. |
| Create a New Certificate | Acquire an Existing Part 135 Charter Company |
|---|---|
|
|
|
FAA - General Requirements for Part 135 Certification