Creating a Part 135 air carrier is a coordinated project involving the company, management personnel, aircraft, manuals, training, FAA compliance, aircraft conformity, proving or validation, and Operations Specifications. This section explains the major work products and decisions without requiring the reader to begin with the detailed certification process.
| Area | Executive Question | Why It Matters |
|---|---|---|
| Certification Options | Should we create a new certificate, acquire an existing company, or modify an existing operation? | The decision affects time, cost, FAA workload, and implementation risk. |
| Operator Requirements | Do we have the company, base, aircraft, programs, and approvals needed to operate? | The operator must satisfy the continuing requirements of Parts 119 and 135. |
| Management Personnel | Do the proposed managers meet FAA qualification and experience requirements? | Management qualification can determine whether certification or transition can proceed. |
| Aircraft | Is the aircraft suitable for the proposed charter operation? | Aircraft size, configuration, records, equipment, and passenger-seat capacity drive many requirements. |
| Manuals and Programs | Are the operating, maintenance, training, safety, and compliance systems documented? | The manuals describe how the company will comply and operate. |
| Training and Qualification | Can the company train, check, qualify, and track its personnel? | Certificates and experience alone do not replace company-specific qualification. |
| Aircraft Conformity | Can we prove that the aircraft and records meet the approved configuration? | Good preparation can make the FAA physical conformity a verification exercise instead of a discovery inspection. |
| Proving and Validation | What must the operator demonstrate before exercising the requested authority? | Certain aircraft and authorizations require proving or validation before revenue operations. |
| Operations Specifications | What is the company actually authorized to do? | OpSpecs define aircraft, areas of operation, limitations, maintenance authority, and special approvals. |
| Preparing to Operate | Can the company safely dispatch a compliant revenue flight? | Certification must become a functioning operating system. |
A buyer does not necessarily need to read every certification detail before evaluating an existing Part 135 company. The following sections provide the fastest practical understanding of what must be transitioned or changed.
| Recommended Section | What the Buyer Learns |
|---|---|
| Certification Options | Why acquiring an existing certificated company differs from starting from scratch. |
| Management Personnel | Who must qualify and what management positions or technical personnel may be required. |
| Aircraft Requirements | How aircraft selection affects maintenance, equipment, staffing, and approval work. |
| Training and Qualification | What must be completed before the buyer's pilots and other personnel can perform assigned duties. |
| Aircraft Conformity | What records, configuration, and physical preparation are required to add the buyer's aircraft. |
| Operations Specifications | What operating authority already exists and what may need to be added for the buyer's operation. |
| Preparing to Operate | What must be working before the transitioned company begins revenue operations. |
| Create a New Certificate | Acquire an Existing Part 135 Charter Company |
|---|---|
|
|
|
A Part 135 air carrier certificate can be created from scratch. The labor-intensive tasks are:
Define the proposed operation.
Prepare comprehensive operations, maintenance, and training manuals.
Show compliance with FAA regulations and guidance requirements.
Hire, train, and qualify flight crew and maintenance personnel.
Complete FAA approval tasks.
|
| Phase | FAA Phase | Applicant / FAA Activity | Gate |
|---|---|---|---|
| 1 | Pre-application | Define the proposed operation, begin the application, and meet with the FAA certification team. | Gate 1 |
| 2 | Formal Application | Submit the application package, manuals, training curricula, compliance statement, management qualifications, proposed OpSpecs, and applicable ED DCTs. | Gate 2 |
| 3 | Design Assessment | FAA evaluates the manuals, programs, procedures, and supporting compliance evidence. | |
| 4 | Performance Assessment | Demonstrate that the aircraft, personnel, training, procedures, and operating systems work as designed. | Gate 3 |
| 5 | Administrative Functions | FAA completes the certification record and issues the certificate and Operations Specifications. | Certificate |
| Start From Scratch | Acquire an Existing Part 135 Charter Company |
|---|---|
Meet operator requirements.
Create manuals and programs.
Complete DCTs and compliance work.
Establish FAA-approved operating systems.
|
Meet operator requirements.
Onboard qualified airmen.
Add the buyer's aircraft.
Modify the existing operation as needed.
|
| Manuals and Training | Design Compliance / DCTs |
|---|---|
General Operations Manual
General Maintenance Manual
Company Training Manual
Aircraft-Specific Training Manual
Minimum Equipment List
International Flight Operations Manual
Flight Attendant Manual, if applicable
|
Review each applicable FAA question.
Identify the regulation and guidance.
Locate the exact manual section.
Enter the manual reference.
Add the supporting manual text.
Explain why a question is not applicable.
Correct any item that cannot be answered Yes.
|
A Data Collection Tool (DCT) is a group of related FAA compliance questions. The applicable DCTs depend on the proposed operation.
| Organizational Management |
Flight Operations |
Operations Management |
Technical Operations |
Onboard Operations |
Ground Operations |
|---|---|---|---|---|---|
Safety Program
Required Personnel
Manual Management
Electronic Records
Safety Policy
Safety Risk Management
Safety Assurance
Safety Promotion
|
Flightcrew Training
Check Pilots/Instructors
Simulators
Outsource Training
Airmen Qualifications
Flight/Duty/Rest
Flight Deck Procedures
Recent Experience
|
Aircraft Performance
Areas/Routes/Airports
Special Navigation
Operational Control
Weight & Balance
MEL/CDL/NEF
Flight Planning
Extended Operations
|
Maintenance Personnel
Maintenance Training
Inspection Requirements
Inspection Schedule
AD Management
Recordkeeping
Airworthiness Release
Repairs/Alterations
|
Flight Attendant Training
Duty/Rest
Cabin Procedures
Carry-on Baggage
Exit Seating
Passenger Handling
|
Station Training
Hazmat Training
Fueling
Line Stations
Cargo Handling
Hazardous Materials
Ground Icing |
76 DCTs |
1,324 Compliance Questions |
| The scope may vary. | |
| DCT Example | Questions | Relative Size |
|---|---|---|
| Recent Experience | 9 | ███ |
| Manual Management | 16 | ██████ |
| Training of Flight Crewmembers | 35 | █████████████ |
| Airman Duties / Flight Deck Procedures | 69 | ██████████████████████████ |
| Answer | Yes or Not Applicable. A No answer identifies an item that must be corrected. |
| Manual Reference | Identify the manual and exact location so the FAA inspector can find the supporting procedure. |
| Supporting Comment | Include the supporting manual text when practical so the inspector does not need to search for it. |
| Not Applicable | Explain why the question does not apply to the proposed operation. |
Creating a certificate from scratch is a tradeoff between time, cost, and reliability.
The major work products are FAA approved.
Flight crew and maintenance personnel must be trained and qualified.
Aircraft compliance must be demonstrated.
The buyer's team is supported by experienced USAC specialists.
|
In a well-prepared acquisition, the goal is to have the buyer operating in approximately 3 to 6 months, subject to FAA availability, aircraft readiness, and completion of required transition work.
Part 135 Air Carrier and Operator Certification
Part 135 Certification Process
There are three practical ways to establish or expand a Part 135 air charter operation. The best path depends on time, cost, aircraft, personnel, and the desired operation.
| Option | Starting Point | Primary Work |
|---|---|---|
| Create a New Certificate | No existing Part 135 operating authority. |
Meet operator requirements.
Develop manuals and training programs.
Complete DCTs and compliance work.
Qualify management and airmen.
Add aircraft and complete FAA approval tasks.
|
| Acquire an Existing Part 135 Charter Company | Acquire the legal entity that already holds a Part 135 certificate and Operations Specifications. |
Meet operator requirements.
Qualify the buyer's management and airmen.
Add or conform the buyer's aircraft.
Modify manuals, OpSpecs, and authorizations as required.
|
| Modify an Existing Operation | The owner already controls a certificated Part 135 operator. |
Add or replace aircraft.
Add personnel.
Expand areas of operation.
Add OpSpecs or special authorizations.
Update manuals and training as required.
|
| Decision Factor | Create New | Acquire Existing | Modify Existing |
|---|---|---|---|
| FAA Foundation | Must be created. | Already exists. | Already exists. |
| Manuals / Programs | Develop and obtain FAA acceptance or approval. | Existing approved or accepted foundation is modified for the buyer's operation. | Modify existing manuals and programs as needed. |
| DCT / Compliance Work | Complete applicable design compliance work. | Existing compliance foundation can be reused and updated. | Complete only the compliance work associated with the change. |
| Personnel | Hire, train, qualify, and obtain required FAA acceptance or approval. | Buyer personnel must be trained, qualified, and accepted or approved as required. | Current personnel remain; new personnel are qualified as required. |
| Aircraft | Aircraft conformity and approval required. | Buyer aircraft must be added and shown compliant. | New or replacement aircraft must be added and shown compliant. |
| Primary Advantage | Build the operation exactly as desired. | Begin with an established certificated company and approved systems. | Expand an operation that already exists. |
Time to operate. How soon must charter operations begin?
Aircraft. Number, type, passenger-seat configuration, and complexity.
Management. Availability of qualified Part 119 management personnel.
Authorizations. Domestic, international, RVSM, MEL, lower takeoff minimums, and other OpSpecs.
Cost and reliability. Balance initial investment against certification workload, FAA review, and execution risk.
|
For an aircraft owner who wants to begin charter operations without creating every certification work product from the beginning, acquisition can significantly reduce the work.
The certificate and Operations Specifications already exist.
The major manuals and compliance systems are already established.
The buyer concentrates on personnel, aircraft, and the desired operation.
Experienced USAC specialists support the transition.
|
The next step is to confirm the buyer, aircraft, management personnel, areas of operation, and required authorizations.
Operator Requirements
Management Personnel
Aircraft
Manuals and Programs
FAA Certification Process
|
A Standard Part 135 operator must have the company, people, aircraft, manuals, programs, and approvals needed to conduct the proposed operation safely and continuously.
| Requirement | What the Operator Needs |
|---|---|
| Company |
|
| Principal Base |
|
| Aircraft |
|
| Management |
|
| Manuals |
|
| Training and Qualification |
|
| Safety Management System |
|
| Economic Authority / Insurance |
|
| Other Required Programs |
|
Aircraft type-certificated for 10 or more passenger seats require a more extensive maintenance system.
| 9 or Fewer Passenger Seats | 10 or More Passenger Seats |
|---|---|
|
|
Does the applicant have the required organization and qualified personnel?
Are the manuals and programs designed to comply with the regulations?
Are the aircraft and records compliant?
Can the applicant train and qualify its personnel?
Can the applicant demonstrate safe, compliant operations on a continuing basis?
| Requirement | Create New | Acquire Existing |
|---|---|---|
| Company / Certificate | Create and certificate the operator. | Acquire the existing certificated entity. |
| Manuals / Programs | Develop and obtain FAA acceptance or approval. | Begin with the existing approved or accepted system and modify as needed. |
| Management / Airmen | Recruit, train, qualify, and obtain required FAA acceptance or approval. | Buyer personnel must still meet the applicable requirements. |
| Aircraft | Conform and obtain approval for the aircraft. | Add or replace aircraft and demonstrate compliance. |
FAA - General Requirements for Part 135 Certification
FAA - Safety Management System
A Standard Part 135 operator must designate qualified people to manage flight operations, pilots, and maintenance. The FAA evaluates the individual, not just the job title.
| Position | Primary Responsibility | FAA Review |
|---|---|---|
| Director of Operations | Operational control, regulatory compliance, company procedures, and day-to-day flight operations. |
|
| Chief Pilot | Pilot qualification, training, checking, proficiency, flightcrew standards, and flightcrew operating procedures. |
|
| Director of Maintenance | Airworthiness, maintenance program control, inspections, maintenance records, and continued compliance. |
|
| Operation | Additional Requirement |
|---|---|
| All Part 135 Operators Subject to Part 5 SMS |
|
| Aircraft Type-Certificated for 10 or More Passenger Seats |
|
| More Than 19 Passenger Seats |
|
Name of each proposed manager.
Resume showing relevant employment and management experience.
Certificates, ratings, and qualifications applicable to the position.
Qualification summary demonstrating compliance with the applicable Part 119 requirements.
Clear duties, responsibilities, authority, and reporting relationships in the company manuals.
| Proposed Operation | Management Implication |
|---|---|
| Simple Domestic Operation | Management responsibilities may be concentrated in a small organization, provided required qualifications and responsibilities are satisfied. |
| Multiple Aircraft / Multiple Pilots | More scheduling, training, checking, maintenance control, records, and operational oversight are required. |
| 10 or More Passenger Seats | The maintenance organization, RII inspection function, records, and continuing airworthiness responsibilities become more extensive. |
| More Than 19 Passenger Seats | A flight attendant crewmember and the associated training and emergency-duty system are required. |
| International / Special Authorizations | Management must understand and support the additional training, manuals, equipment, records, and OpSpec requirements. |
The FAA may approve a deviation from certain Part 119 management position or qualification requirements when justified by the size and scope of the operation or comparable experience. A deviation is an FAA determination and should not be assumed in the business plan.
| Question | Why It Matters |
|---|---|
| Do we have qualified managers? | Management qualification can determine whether the certification or transition can proceed. |
| Do we have the required technical personnel? | Larger and more complex aircraft add maintenance inspection and crewmember requirements. |
| Can the team perform the job after certification? | The requirement is continuing operational control and compliance, not simply passing an initial review. |
| Are responsibilities clearly assigned? | Manuals, OpSpecs, SMS, and company organization must show who has authority and responsibility. |
14 CFR 14 CFR 119.69 - Part 135 Management Personnel
14 CFR 14 CFR 119.71 - Management Qualifications
14 CFR 5.25 - Required Safety Management Personnel
14 CFR 135.429 - Required Inspection Personnel
The aircraft drives much of the Part 135 certification workload. Its size, equipment, maintenance program, records, and intended operation determine many of the FAA requirements.
| Requirement | What the Operator Must Show |
|---|---|
| Registration / Airworthiness |
|
| Exclusive Use |
|
| Configuration / Equipment |
|
| Maintenance Records |
|
The operator must have exclusive use of at least one aircraft. FAA guidance generally requires ownership or a lease agreement covering at least six continuous months from certification.
USAC can provide a dry-lease agreement that has been approved previously and is frequently accepted by the certificate-holding district office.
If the agreement is materially modified or replaced, FAA legal counsel review may be required.
In USAC's experience, legal review of a revised lease typically takes approximately two to three weeks.
| 9 or Fewer Passenger Seats | 10 or More Passenger Seats | More Than 19 Passenger Seats |
|---|---|---|
|
|
|
|
Before an aircraft is approved for Part 135 operations, the FAA evaluates the aircraft and records to determine whether the aircraft conforms to its approved configuration and the requirements of the proposed operation.
Registration and airworthiness documents.
Aircraft equipment and configuration.
Maintenance status and inspection history.
Airworthiness Directive compliance.
Life-limited components and overhaul status.
Required instruments, avionics, emergency equipment, and placards.
| When Required | Purpose |
|---|---|
| Turbojet / Certain Two-Pilot Aircraft | Proving tests demonstrate the operator can conduct the proposed operation safely and in compliance with Part 135. |
| New Aircraft or New Kind of Operation | Validation may be required when adding certain aircraft, international operations, Class II navigation, or special authorizations. |
| FAA Determination | The FAA determines the testing needed based on the aircraft, the proposed operation, and the operator's prior experience. |
| Question | Why It Matters |
|---|---|
| Is the aircraft already Part 135 ready? | Incomplete records, configuration issues, or overdue maintenance can delay approval. |
| How many passenger seats is it type-certificated for? | The 10-seat threshold changes the maintenance system; more than 19 adds flight attendant requirements. |
| What operations are planned? | IFR, international, RVSM, MEL, lower minimums, and other authorizations can add equipment and approval work. |
| Has this type been operated by the certificate holder? | Proving or validation requirements may apply. |
The buyer can select the aircraft that best fits the intended charter operation.
USAC can evaluate the aircraft and maintenance records before the FAA conformity review.
The aircraft is added to the existing certificate and Operations Specifications after applicable FAA requirements are satisfied.
14 CFR 135.25 - Aircraft Requirements
14 CFR 135.143 - General Aircraft Equipment Requirements
14 CFR 135.145 - Proving and Validation Tests
14 CFR 135.411 - Maintenance Applicability
The manuals describe how the air carrier will operate. The FAA reviews them to determine whether the proposed operation complies with the regulations and can be performed safely.
| Manual / Program | Purpose |
|---|---|
| General Operations Manual | Defines operational control, company organization, flight operations, crewmember duties, records, procedures, and operating policies. |
| General Maintenance Manual | Defines the maintenance organization, maintenance program, inspection system, records, and continuing airworthiness procedures. A separate GMM is required for aircraft type-certificated for 10 or more passenger seats. |
| Company Training Manual | Defines the training system, curriculum structure, qualification standards, checking, recurrent training, records, and instructor/check-pilot functions. |
| Aircraft-Specific Training | Provides the ground, flight, systems, limitations, procedures, emergency, and qualification training for each aircraft type. |
| Minimum Equipment List | Allows specified inoperative equipment to be deferred under approved conditions, procedures, limitations, and repair intervals. |
| Hazardous Materials Program | Defines whether the operator will carry or will-not-carry hazardous materials and establishes the required training and procedures. |
| Safety Management System | Defines safety policy, safety risk management, safety assurance, safety promotion, responsibilities, records, and performance monitoring. |
| International Flight Operations Manual | Supports international areas of operation, navigation, communications, oceanic procedures, flight planning, customs, and special authorizations, as applicable. |
| Flight Attendant Manual | Required when the operation requires flight attendants; defines duties, training, emergency procedures, passenger handling, and cabin-safety responsibilities. |
Basic indoctrination and company procedures.
Emergency and Crew Resource Management training.
Initial aircraft ground and flight training.
Recurrent, requalification, transition, differences, and upgrade training, as applicable.
Hazardous materials training.
Flight attendant training when required.
| Step | Purpose |
|---|---|
| 1. Regulation | Identify the applicable regulatory and FAA guidance requirement. |
| 2. Manual | Describe how the company complies. |
| 3. DCT Response | Point the FAA inspector to the exact manual and location. |
| 4. Training | Teach personnel how to perform the approved procedure. |
| 5. Records | Document that the required action, training, inspection, or qualification was completed. |
The manuals define the procedures. Operations software turns those procedures into the forms, records, alerts, qualification tracking, maintenance controls, and other tools used to operate the company.
Scheduling and dispatch records.
Pilot qualification and training records.
Aircraft conformity and maintenance tracking.
Safety reporting and SMS records.
Controlled forms and required operational records.
| Question | Why It Matters |
|---|---|
| Are the manuals complete? | Required manuals and training programs must be submitted for FAA review as part of the formal application. |
| Do the manuals match the aircraft and operation? | Generic documents are not enough; the procedures must support the actual aircraft, personnel, authorizations, and areas of operation. |
| Can employees use the procedures? | FAA approval is only the beginning. Personnel must be trained to perform the procedures correctly. |
| Can compliance be demonstrated? | The company must produce records showing that required training, maintenance, inspections, qualifications, and operational controls occurred. |
| Create a New Certificate | Acquire an Existing Part 135 Charter Company |
|---|---|
|
|
|
FAA - General Requirements for Part 135 Certification
FAA - Part 135 Certification Process
14 CFR 135.21 - Manual Requirements
14 CFR 135.23 - Manual Contents
The FAA approves the training program and evaluates whether each person is trained, checked, qualified, and current for the duties assigned.
| Requirement | What Must Be Completed |
|---|---|
| Company Indoctrination | Company organization, manuals, operating procedures, regulatory requirements, and employee responsibilities. |
| Emergency / CRM Training | Emergency duties, equipment, procedures, and Crew Resource Management appropriate to the operation. |
| Aircraft Ground Training | Aircraft systems, performance, limitations, weight and balance, normal procedures, abnormal procedures, and emergency procedures. |
| Aircraft Flight Training | Required maneuvers, procedures, profiles, instrument procedures, normal operations, abnormal operations, and emergency operations. |
| Testing and Checking | Required knowledge tests, competency checks, instrument proficiency checks, and line checks, as applicable. |
| Recent Experience / Currency | Pilots must maintain the recent experience and recurrent qualification required for the operation. |
Basic indoctrination.
General emergency training.
Crew Resource Management training.
Aircraft-specific ground training.
Aircraft-specific flight training.
Initial, transition, upgrade, differences, requalification, and recurrent training, as applicable.
Hazardous materials training.
International or special-authorization training, when applicable.
| Personnel | Training / Qualification |
|---|---|
| Maintenance Personnel | Training and qualification must support the assigned inspection, maintenance, records, airworthiness, and maintenance-control duties. |
| RII Inspectors | For the applicable 10-or-more maintenance system, Required Inspection Item personnel must be certificated, trained, qualified, and authorized for the inspections they perform. |
| Flight Attendants | When required, flight attendants must complete the approved initial and recurrent training for assigned duties and emergency responsibilities. |
| Instructors / Check Pilots | Persons providing required training, testing, or checking must meet the applicable qualification and authorization requirements. |
Qualification is not complete until the operator can document it. Training records show what was completed, when it was completed, who provided or evaluated it, and when recurrent training or checking is due.
Employee and pilot qualification records.
Training completion records.
Testing and checking records.
Recurrent due dates and qualification status.
Instructor and check-pilot qualifications.
| Question | Why It Matters |
|---|---|
| Are the people qualified now? | Existing certificates and experience may reduce training, but they do not replace the operator's approved training and qualification requirements. |
| Is aircraft-specific training available? | Training availability can affect aircraft selection, certification schedule, and transition cost. |
| Who will conduct the training and checks? | The operator may use qualified company personnel, approved training centers, or other authorized resources, depending on the program. |
| Can qualification be tracked? | Expired training or checking can immediately remove a person from an assigned duty. |
| Create a New Certificate | Acquire an Existing Part 135 Charter Company |
|---|---|
|
|
|
FAA - General Requirements for Part 135 Certification
14 CFR 135.323 - Training Program General
14 CFR 135.329 - Crewmember Training Requirements
14 CFR 135.331 - Crewmember Emergency Training
14 CFR 135.345 - Pilot Ground Training
Aircraft conformity verifies that the aircraft, records, equipment, and configuration support the proposed Part 135 operation. USAC prepares the conformity record before the FAA inspection so the inspector can quickly verify compliance.
The USAC operations software organizes the conformity documents in a shared Aircraft Compliance page. Multiple users can prepare and review the record, and the FAA can be provided access to the same organized information.
| Documents and Authority | Configuration and Approvals | Inspection and Operation |
|---|---|---|
|
|
|
|
| Step | Action |
|---|---|
| 1. Submit |
|
| 2. Organize |
|
| 3. Review |
|
| 4. Confirm |
|
| 5. Perform |
|
| 6. Correct |
|
The maintenance records are checked against the maintenance tracking system and the underlying logbook entries. The objective is to prove that the electronic status and the aircraft records agree.
Current inspection status and maintenance program requirements.
Airworthiness Directives and recurring due dates.
Life-limited and time-limited components.
Major repairs and alterations, FAA Form 337s, STCs, and ICAs.
Equipment list and installed equipment.
Weight and balance and applicable scale/calibration records.
Fireblocking, RVSM, and other aircraft-specific requirements, when applicable.
When the records and Aircraft Compliance page are complete, the physical inspection becomes a verification exercise rather than a discovery exercise.
Verify placards and equipment serial numbers.
Confirm required aircraft documents and manuals are aboard.
Confirm briefing cards and emergency equipment are aboard, current, and properly located.
Confirm the aircraft configuration agrees with the conformity record.
| Capability | Benefit |
|---|---|
| Shared Web Record | Operations, maintenance, management, and FAA personnel can work from the same organized conformity record. |
| Document Checklist | Missing and incomplete documents are visible before the FAA inspection. |
| GMM Procedure | The conformity process is documented and repeatable rather than recreated for each aircraft. |
| Pre-Conformity Review | Records and aircraft discrepancies are corrected before the FAA review. |
| Efficient FAA Review | A well-prepared package allows the FAA physical conformity to concentrate on verification. USAC normally plans about a half day for the physical conformity. |
As an example of the preparation process, USAC is currently using this system to prepare a Falcon 50 conformity package on a seven-day preparation schedule. Actual FAA review time depends on aircraft condition, records, configuration, inspector availability, and discrepancies found.
FAA - General Requirements for Part 135 Certification
Proving and validation demonstrate that the operator can use its aircraft, people, manuals, training, and operating systems safely and in compliance with Part 135.
| Test | When It Applies | Purpose |
|---|---|---|
| Proving Tests | Generally required when the certificate holder has not previously proved a turbojet airplane, or another aircraft for which two pilots are required for VFR operations, under Part 135. | Full-scale simulation of the proposed revenue operation. |
| Validation Tests | Required for specified new aircraft and authorizations, including certain international operations, Class II navigation, and special performance or operational authorizations. | Demonstrate that the operator can safely conduct the specific operation or authorization. |
When required by 14 CFR 135.145, proving tests include at least 25 hours acceptable to the FAA.
Five hours of night operations if night operations will be authorized.
Five instrument approaches under simulated or actual conditions if IFR operations will be authorized.
Operations into a representative number of en route airports determined by the FAA.
Passengers are not carried except persons needed for the test or FAA-designated observers.
| Area | Demonstration |
|---|---|
| Operational Control | Dispatch/release decisions, flight following, weather, maintenance status, crew qualification, and management oversight. |
| Flightcrew | Use of company procedures, checklists, MEL, abnormal procedures, CRM, and aircraft-specific training. |
| Maintenance | Aircraft status, maintenance control, discrepancies, return-to-service procedures, and required records. |
| Manuals and Software | The procedures and operating tools work in actual operations as described in the approved manuals. |
| Airports / Areas | The operator can safely conduct the routes, airports, navigation, and special operations requested. |
The FAA may use an acceptable demonstration method other than an actual flight when the operator can demonstrate competence and compliance without flying. Proving and validation tests may also be conducted at the same time when appropriate.
Aircraft conformity complete and discrepancies corrected.
Manuals and applicable programs approved or accepted.
Flightcrew and required personnel trained, checked, and current.
MEL, maintenance control, dispatch, flight-following, and record systems operational.
Required airports, routes, scenarios, and special authorizations included in the demonstration plan.
Schedule of Events coordinated with the FAA certification team.
| Question | Why It Matters |
|---|---|
| Is proving required? | A new turbojet operation can require at least 25 hours of proving before revenue operation. |
| What must be validated? | Aircraft, international areas, Class II navigation, or special authorizations may trigger validation work. |
| Is the operation ready before the test? | Proving runs are intended to demonstrate an operating system, not finish building one. |
| Can demonstrations be combined? | The FAA may permit proving and validation to be accomplished together when appropriate. |
| Create a New Certificate | Acquire an Existing Part 135 Charter Company |
|---|---|
|
|
|
FAA - General Requirements for Part 135 Certification
Operations Specifications, or OpSpecs, define what the air carrier is authorized to do. They identify the aircraft, areas of operation, operating limitations, training, maintenance, and special approvals granted by the FAA.
| Part | Primary Subject | Examples from USAC Airways 699 |
|---|---|---|
| A | General Authority and Programs |
|
| B | Areas of Operation and Navigation |
|
| C | Terminal and IFR Operations |
|
| D | Aircraft and Maintenance Authorizations |
|
| E | Weight and Balance |
|
B050 is a good example of how an OpSpec becomes real operating authority. It identifies the geographic areas in which the carrier may conduct authorized operations, subject to the limitations, equipment, training, and procedures that support those areas.
| USAC Airways 699 | Practical Meaning |
|---|---|
|
|
|
| OpSpec | Why It Matters |
|---|---|
| A003 | Identifies the aircraft authorized for operation. |
| A006 | Identifies required management personnel. |
| A008 | Defines operational-control responsibilities. |
| A061 | Authorizes the Electronic Flight Bag program. |
| B050 | Defines authorized geographic areas of en route operation. |
| C057 | Authorizes IFR takeoff minimums for Part 135 airplane operations. |
| D085 | Lists the aircraft authorized on the certificate. |
| D095 | Authorizes use of the Minimum Equipment List. |
| Question | Why It Matters |
|---|---|
| What authority already exists? | An existing certificate can provide a useful operating foundation that does not need to be rebuilt from zero. |
| What does the buyer want to operate? | Aircraft, areas, and special authorizations determine which OpSpecs must be added or changed. |
| What should be retained? | Existing useful authorizations can reduce transition work and preserve operating flexibility. |
| What should be added later? | International and special authorizations can be phased in after the core operation is stable. |
Begin with an existing certificate and Operations Specifications.
Retain useful authorizations such as domestic and regional international authority.
Add the buyer's aircraft and requested areas of operation.
Add specialized authority as the operation grows.
FAA - Part 135 Air Carrier and Operator Certification
Certification is complete only when the company can conduct the operation safely, legally, and repeatedly. The transition from certification project to operating air carrier requires the aircraft, people, records, and systems to work together.
| Area | Ready-to-Operate Condition |
|---|---|
| Certificate / OpSpecs | Certificate and required Operations Specifications are issued and current. |
| Aircraft | Aircraft conformity is complete, required equipment is installed, and the aircraft is listed in the applicable OpSpecs. |
| Management | Required managers are accepted or approved and performing their assigned responsibilities. |
| Flightcrew | Pilots are trained, checked, qualified, and current for the aircraft and operation. |
| Maintenance | Maintenance-control, inspection, discrepancy, records, and airworthiness systems are operational. |
| Manuals / Training | Approved or accepted manuals and training programs reflect the actual operation. |
| Safety | SMS reporting, risk management, assurance, and safety-promotion processes are operating. |
| Operational Control | Scheduling, dispatch, flight following, weather, crew qualification, aircraft status, and record systems are working. |
Confirm every aircraft and airman is current and authorized.
Verify recurring training, inspections, checks, and records are being tracked.
Test scheduling, dispatch, flight following, maintenance control, and EFB processes.
Confirm required forms and electronic records are available and controlled.
Verify customer, passenger, baggage, and charter-flight procedures are understood.
Confirm the management team knows what must be reported to the FAA and when.
| Certification Project | Operating Air Carrier |
|---|---|
| Prove the manuals describe compliant procedures. | Use those procedures on every flight. |
| Train and qualify the initial personnel. | Track recurrent training, checking, and qualification continuously. |
| Conform the initial aircraft. | Maintain continuous airworthiness and accurate aircraft records. |
| Obtain the initial OpSpecs. | Keep authority current and add new capabilities deliberately. |
| Demonstrate SMS processes. | Measure safety performance and correct problems. |
| Question | Why It Matters |
|---|---|
| Can the company dispatch a compliant flight today? | Certification documents have value only if the operation can use them correctly. |
| Are due dates controlled? | Expired training, inspections, or authorizations can stop an aircraft or airman immediately. |
| Can management see the status? | Operational software should show aircraft, pilot, training, maintenance, and compliance status before a flight is assigned. |
| Can the operation grow? | A stable operating system makes it easier to add aircraft, pilots, areas of operation, and special authorizations. |
Acquisition changes the project from building an air carrier from scratch to transitioning an established operation. The buyer's team can concentrate on the aircraft, people, desired authorizations, and business operation while retaining the existing certification foundation.
Existing certificate and OpSpecs.
Existing manuals and compliance system.
Existing training and records structure.
Existing operational-control and safety systems.
Experienced USAC support during transition.